TCM490: Telecommunications Management Senior Project
Microsoft Project Management File


Introduction

The Microsoft Project Management Software (currently Project 98) is one of the tools you'll be using to design and track your project from Start-Up Phase to Close-Out Phase. A Starter Project Management File will be provided: tcm490-projectoutline.mpp.

The chart develops from your Project Description, WBS, Learning Contracts, and other support documents. The Gantt and Pert charts will be referenced at each report or presentation.

During the implementation phase, there must be a status report each week. For tracking purposes, a minimum of four to six reports are required.

Here is an example of a Microsoft Project Management file showing the Gantt Chart.
Click to enlarge

Here is another example of a Gantt Chart.
Click to enlarge

Here is an example of a Pert Chart for the Gantt Chart above.
Click to enlarge

The relationship between the project file and support documents must be clear.